Print Friendly, PDF & Email

Project Detail

Wind – Dry Lake II Wind Farm 69kV/34.5kV Substation and Collector System

Dry-Lake-II-03      Dry-Lake-II-01      Dry-Lake-II-02

Location: Arizona

Description: MYR Group subsidiary, Sturgeon Electric was selected to construct a new 69kV/34.5kV substation and collector system for Phase II. Beginning in late July 2010, Sturgeon Electric subcontractors

started substation foundations and trenching work in the collection field. Sturgeon Electric crews followed shortly thereafter, beginning work on substation construction and termination of approximately 100,000 feet of 3-phase cable in the collection field. Sturgeon Electric crews were also able to handle the portion of commercial and industrial work required on the project – wiring from GSU transformers into the towers and installation of shunt trip devices.

Completion Date: 2010

Work Performed By: Sturgeon Electric Company, Inc., a subsidiary of MYR Group

Client: Iberdrola Renewables

PDF View Project Write-Up